Case Reference
Our company provides a specific packaging solution for each customer, based on the customer's drawings, ideas, or actual samples, on this basis to make changes, and then combined with the customer's production line, plant conditions, market conditions, product characteristics and other adjustments, and finally provide customers with a satisfactory solution.
Customization Design Procedure
3 days
IDEA
15 days
DESIGN
10 days
SAMPLE MOLD
10 days
SAMPLE
10 days
SAMPLE TEST AND RECORD
EXPRESS SAMPLE
7 days
SAMPLE APPROVED
15days
PRE-PRODUCTION WORKS
20days
MASS PRODUCTION MOLD
30 days
MASS PRODUCTION
Long-term
DELIVERY
AFTER-SALE FOLLOWING UP
Customization Design Request
Upon the information you provided, we'd analyze it and offer the most comprehensive solution.